Posted on Wednesday November 30, 2011
The Aberdeen Carolina and Western Railroad work on the crossings on South Street has been completed.
January 27, 2012
The work on the South Street railroad crossings has been completed.
__________________________________________________________________
December 1, 2011
The Aberdeen Carolina and Western Railroad will be working with the Town of Aberdeen to replace one crossing on South Street and increase the height of two other crossings on South Street.
This work is scheduled to begin on January 9, 2012 and will be completed as quickly as possible.
This project will also affect Sycamore Street, so it would be advisable to avoid this intersection altogether.
Parts of each street will be closed for this two week period. Once the railroad has completed the work, the Town will be patching all needed areas and weather permitting will repave South Street from Poplar to N.C. Hwy. 211.